10 July 2019: Abbotsford Bridge – progress update July 2019

Temporary river diversion works are complete and the carriageway surface has been carefully removed to expose utility services that run through the structure.  

It will not be necessary for BT cables and a main sewer pipe to be diverted during the works as we have constructed a temporary structure to support these pipes and cables during the construction period. This is now in place and operational.

Other pipes and cables require diverting temporarily over the watercourse (electric, gas and water supplies).  A second scaffold system has been constructed in advance of the works. 

These temporary diversions will be carried out by the respective utility provider.  We have experienced an unplanned delay with the diversion of electricity cables, however the diversion of water supplies is expected to begin in the coming days and gas diversions are due to commence next week.

Once the diversion of utility services are complete, works can begin to remove the existing structure.

10 June 2019: Abbotsford Bridge – progress update

Since the closure of Abbotsford Bridge on 13 May, a site compound has been established and a temporary footway and lighting installed to provide a pedestrian route during the construction period. This is now in public use.


A temporary bridge is in the process of being installed to support utility supplies that require diverting temporarily. In the coming days electrical diversions are set to begin.

River diversion works are also in progress.

To support local people and businesses, additional signage has been placed on the local road network.

We will continue to post updates on this webpage as the scheme progresses.

Hall Road Closure Update

Update on closure of Hall Road for up to 6 Months

Hall Road bridge is falling down

Abbotsford Bridge is on Hall Road, about a quarter of a mile down from The Crown. Amazingly the original structure is 140 years old, and consists of a cast iron deck supported on cast iron girders.

Structural engineers from ECC have visited it and determined it is at the end of its life and a new bridge is needed. The 3-day closure in March was preparatory work to clear vegetation.

May to November for new bridge

ECC say the main works are to commence on 10th May and expect to take about six months to complete (maybe it will only be 4 months, but until they lift the old bridge it is difficult to tell, and they say poor weather may delay them). That means they are being cautious with their estimates. As part of the work they will temporarily relocate the pedestrian footbridge, the water course and utilities.

Hall Road will be CLOSED

During this time ECC say that unfortunately a full closure of the road will be necessary. They say that they will put up official diversion signs.

ECC has put up a webpage to provide details and updates. The link is:  https://www.essexhighways.org/highway-schemes-and-developments/highway-schemes/abbotsford-bridge-hall-road-elsenham.aspx

You should be able to find the link through  https://essex.gov.uk  and then enter Abbotsford Bridge in the ‘I’m looking for’ box.  It should then be the first on the list.

Road Closure

Grove Hill will be closed from the 1st April to 3rd May.

Cars:
Please consult the below website for up to date information and diversions
https://roadworks.org/?107838465

Buses:
this will affect the bus time tables, drivers are handing out new timetables.  Alternatively please download it here

For all up to date information please visit their website: https://trustybus.net/timetables/

Elsenham Parish Council have not received one yet that we our selves can distribute.